Kennedy Bay Golf Club House Update

Kennedy Bay Golf Club House Update

18 Nov 2020

Clearer weather in October has led to good progress on site with the completion of the suspended cantilevered deck. Minimal rainfall this month ensured the execution of concrete pours as planned.
 
The coming weeks will tick off some significant milestones.
      - Site prep for cranage and steel delivery commenced (steel erection thereafter)
      - Concrete honing has begun
      - Window and kitchen shop drawings are underway
      - Procurement of ceilings, wall linings, and landscaping initiated.
EMCO Building is pleased to be working with the following teams to deliver a quality project.
 
Client: Western Australia Beach and Golf Resort Pty Ltd
Development Manager: Place Development Australia
Architect: Gresley Abas
Superintendent: David Hunt
QS: Donald Cant Watts Corke
Consultants:
      - Structural & Electrical Engineer - Forth Consulting
      - Civil Engineer - Cossill & Webley Consulting Engineers
      - Mechanical Engineer - Link Engineering Consultants
      - Hydraulic Engineer – Iconic Design Australia
      - Fire Engineer - Xero Fire & Risk
      - Landscape Architect - Emerge Associates
      - NCC – Resolve