South Regional TAFE Esperance - New Replacement Campus Update

South Regional TAFE Esperance - New Replacement Campus Update

10 Mar 2021

Work continues as scheduled on the new Replacement Campus in Esperance with Plumbing, Electrical, and Mechanical services reticulation at about 85% complete.
 
Other milestones include the completion of brickwork and roof cover, along with the installation of a new Transformer. Additionally, painting and external concrete paving has commenced and gyrock lining is well underway.
 
Milestones coming up include:
  - Timber decking commencing tomorrow
  - Administration building scheduled for completion in 3 weeks
 
EMCO Building is pleased to be working with the following teams to deliver a quality project.
 


Client:
  - Building Management Works
Architect:
  - Hassell Studio
Quantity Surveyor:
  - Rider Levett Bucknall
Consultants:
  - Civil & Structural Engineering / Stantec
  - Electrical Engineer / Best Consultants
  - Hydraulic & Fire Engineer / Hydraulic Design Australia
  - Mechanical Engineer / Stevens McGann Willcock & Copping