Early stage moving forward . We have completed the general Excavation, also completed the detailed excavation in ready to install reinforcement to footings.

Half footing poured & the first lift shaft has been constructed, with first couple of courses on the strip footings & sample panels done. Service pre-lays done, trenches cut to allow pre-lays to existing slabs.

New roof installed to stage 1 section of project & we will start structural steel erection tomorrow.