John Wollaston Anglican Community School

John Wollaston Anglican Community School

27 Mar 2017

Full steam ahead footings and slabs poured. The last of the civil works is getting finished off with the connections of stormwater and drainage.

Structural Steel shop drawings have been approved and steel is in production.

Bricks have been delivered to make a start in the ablution area.

We have started have made a start with running cable tray and wiring to the existing buildings. We plan to make both Electrical & Hydraulic main connections to occur during the school holidays.