South Regional Tafe Esperance - New Replacement Campus Update

South Regional Tafe Esperance - New Replacement Campus Update

2 Feb 2021

There’s been a plenty happening on the New Replacement Campus Project since our last blog back in September.

    - Roof sheeting is at 95% cover;
    - Partition framing work is all but complete and gyprock is underway;
    - Mechanical ductwork has been installed to the Admin Block;
    - Electrical installation is well under way to Block A and B;
    - Window installation in progress to both Block A and B.
 
Final Earthworks are scheduled to commence mid to late March along with landscaping works.
 
EMCO Building is pleased to be working with the following teams to deliver a quality project.
 
Client: BMW
Architect: Hassell Studio
QS: Rider Levett Bucknall
Consultants:
    - Civil and Structural Engineering - Stantec
    - Electrical Engineer – Best Consultants
    - Hydraulic & Fire Engineer – Hydraulic Design Australia
    - Mechanical Engineer – Stevens McGann Willcock & Copping