Challenger Institute Of Technology

Challenger Institute Of Technology

1 Feb 2017

We have accomplished another milestone this month being the completion of the Structural Steel level 2 Roof. By achieving this milestone this opens up the final level which allows the trades continuity of work.

In addition to the above milestones the external services, windows and wall cladding contractors are able to schedule and commence works.

With the ground and first floors fit outs being ahead of schedule we now have the opportunity to commence with the finishing trades such as tilers, painters etc.


 